Ormiston Cliff Park School
Overview
The Summer 22 washroom works at Ormiston Cliff Park included the refurbishment of 3 washrooms at the site.
The project
The project commenced with the strip out of existing washrooms and then all elements of the washrooms were refurbished.
New ventilation was installed along with a suspended ceiling and LED lighting. All plumbing, electrical and painting work was included at this stage too. Then non-slip vinyl flooring was put down along with hygienic wall cladding on the walls as they are both easy to clean and maintain.
Durable solid-grade laminate cubicles, duct panelling and vanity units completed the main installation. We installed sensor hand dryers and refitted existing dispensers to complete
the new washrooms.
Challenges
In one of the washrooms, access to an inspection chamber wasn’t initially required. However, it was decided later on that access would be required – by which time the vinyl flooring had been laid.
We liaised with the Academy and the drain company management to revise the project programme to accommodate the unplanned work and minimise the extended time on the project.
The result
We have since completed another project at the academy and received the following feedback:
“Another very successful project completed over the Christmas period. The quality of work is phenomenal and the work ethic and flexibility of the team on site are a credit. ”
M Steele – Facilities Manager
Ormiston Cliff Park Primary Academy
GET IN TOUCH
With over twenty years in the business, we are experts in commercial washroom refurbishments and in the last year alone, we’ve refurbished over 300 washrooms over 90 sites. If you have a project coming up, please just take a moment to get in touch with our friendly team and we can come out and offer a free consultation. We look forward to hearing from you.